Substation upgrade and new main switchboard for a packaging plant
A plant in Guarulhos ran its 1994 substation with no discrimination and no earthing record. I redrew the single-line diagram, the me…
- Ano2025
- Escoposurvey + design
- Entrega23 days
A Curitiba condominium approved 48 bays with chargers and the substation could not follow. I ran the load study with the building manager, reserved the demand and split the metering: each unit pays what it draws, with no assembly argument.
The minutes allowed twelve 7 kW chargers fitted by the residents themselves, wired straight into the block board. That board was six years old and had no spare capacity: existing load already reached 84% of the contracted demand during the afternoon peak. Installed as approved, the first twelve chargers would have tripped the main breaker inside the garage.
The specification carried one clause the building manager asked for in writing: no individual connection without sign-off from the technical lead. With 21 days of metering on record, NBR 17019-1 stopped being a corridor argument and became a specification — the one that backs the ART record and the garage insurance.
A plant in Guarulhos ran its 1994 substation with no discrimination and no earthing record. I redrew the single-line diagram, the me…
A 1,850 m² store in Brasilia replaced burnt luminaires like-for-like. I mapped the real illuminance of each sales zone and redesigne…
A townhouse in Belo Horizonte still had its 1990s board, no protective conductor and three mixed circuits. I rebuilt the board, the …