Solar energy · 2023

1.15 MWp ground-mounted solar plant: design, tests and filing with the utility

A rural producer near Goiania wanted relief on the pumping bill. I modelled generation, losses and payback before any module purchase, then designed the layout, protection and earthing and witnessed commissioning.

Distributed generation String layout Commissioning Utility approval Study + design + tests
ClientRural producer (name withheld)
LocationGoiânia, GO
Year2023
Load610 kW average demand
Area2.8 ha
Standard appliedNBR 16690 · NBR 5410 · ANEEL Resolution 1,059/2023
Duration95 days
Resultsimulated yield of 1,940 MWh a year inside the band expected for the region
1.15 MWp ground-mounted solar plant: design, tests and filing with the utility

The pumping bill before the panels

The quote on the table carried 2,310 modules and no word about the load curve. Irrigation pulled eight pumps in shifts that did not match midday sun, and the consumer unit was on the regulated A tariff with time-of-use pricing. Solar without reading the load curve is an equipment purchase, not a design.

What went into the spreadsheet

StageCriterionFigure adopted
Solar resourceSite mean irradiance over a 10-year history5.4 kWh/m²·day
ArrayString voltage inside inverter limits with thermal margin28 strings · 2 inverters
LossesRow-to-row shading, temperature, cabling and dust13.8% per year
Consumption coveredCompared against 12 months of bills, no remote self-consumption71% of annual energy
  • Ground-mount layout with steel piles and spacing reviewed in the third irrigation month, when the grass grows tall
  • Surge protection on the DC side and on the AC side, with a visible load-break disconnecting switch
  • A dedicated earthing system, mesh bonded to the metering board in line with NBR 16690
  • Conductor identification, disconnect boxes and the labelling the distributor requires at filing

Commissioning recorded open-circuit voltage per string, insulation resistance, device tripping and the production curve over the first 30 days. The model pointed at 1,940 MWh a year; the first two metered cycles landed 4% below, inside the band the model itself allowed for months with above-average rain. Payback is a projection, not a contract: that is how it is written in the specification.